Greek Village Phase 4- Subcontractor Prequalification Advertisement

Frank L. Blum Construction, Inc. has been selected as the Construction Manager @ Risk by North Carolina State University and is seeking to prequalify construction trade and specialty contractors to submit bids for furnishing labor, materials, equipment, and tools for the Greek Village Phase 4 Buildings Package project in Raleigh, NC.

PROJECT DESCRIPTION: Greek Village Phase 4 Buildings Package includes the construction and site infrastructure for three new, residential-style buildings located within NC State’s existing Greek Village. The apartment building will be a 56,132 SF, 4-story, wood-framed building with 147 total beds arranged in apartment-style suites with a central corridor.  The 3-story Townhouse A is a total of 22,786 SF and will have 75 total beds and will include a commercial kitchen on the ground floor.  Townhouse B has 57 beds at 17,136 SF and will also be 3-stories.  All three buildings will have a combination of brick and cementitious veneer with asphalt shingles and aluminum gutters and an interior elevator for ADA access. Building construction is scheduled to start in Q3 of 2021 and must be completed by early 2023. 

There will be a HUB outreach meeting to provide additional information about the project on Monday, May 17, 2021, @ 4 pm.  You can register for this meeting online at https://flblum.zoom.us/meeting/register/tZcoduGorjItGtGLOHWEAGGu8Dzsk8LmVD3C

Subcontractors may choose to prequalify for multiple bid packages.

Principal trade and specialty contractors are solicited for the following bid packages:

Bid Package

Bid Package Description

Estimated Budget

BP0100

General Trades

$425,000

BP0174

Final Cleaning

$45,000

BP0300

Turnkey Concrete

$550,000

BP0400

Turnkey Masonry

$1,580,000

BP0500

Turnkey Structural & Miscellaneous Steel

$475,000

BP0611

Wood Framing

$2,200,000

BP0620

Finish Carpentry, Millwork & Casework

$410,000

BP0660

FRP

$100,000

BP0710

Caulking & Waterproofing

$60,000

BP0720

Building Insulation

$375,000

BP0746

Exterior Siding, Soffits, & Panels

$260,000

BP0750

Roofing

$375,000

BP0781

Fireproofing & Intumescent Paint

$20,000

BP0810

Turnkey Doors, Frames & Hardware

$825,000

BP0840

Storefronts & Glazing

$35,000

BP0850

Windows

$240,000

BP0920

Gypsum Board Assemblies

$1,050,000

BP0930

Hard Tile

$20,000

BP0950

Acoustic Ceilings

$45,000

BP0960

Resilient & Carpet Flooring

$750,000

BP0984

Acoustical Panels

$30,000

BP0990

Painting

$655,000

BP1000

Specialties

$140,000

BP1236

Countertops

$150,000

BP1420

Conveying Systems

$400,000

BP2100

Fire Protection

$540,000

BP2200

Plumbing

$2,200,000

BP2300

HVAC

$1,800,000

BP2600

Electrical & Fire Alarm

$3,030,000

BP2621

Cabling

$330,000

BP3100

Sitework

$270,000

BP3213

Concrete Sidewalks

$120,000

BP3300

Site Utilities

$283,000

Additional packages may be added and deleted by the Owner and Construction Manager.

Frank L. Blum Construction, Inc. has a long-standing commitment to maximize minority and other HUB participation on all of our projects, and we recognize the importance the University of North Carolina places on minority and HUB participation for all of their projects. Our goal is to achieve a minimum of 20% minority participation on this project.

Prequalification forms can be obtained from our online plan room http://www.flblum.com/subcontractors.php.   Completed prequalification forms should be submitted to Kari Hiatt by May 21, 2021, via email (khiatt@flblum.com) or mail (830 NE 25th St., Winston-Salem, NC  27105).  Target bid date is July 2021.