Kilgore Hall

Asset:

Kilgore Hall – First Floor

Project Manager:

Steven Eisenberg

Total Cost:

$58,769

Cost Per Square Foot:

$N/A

Completion Date:

Jun 13, 2014

Narrative:

Steven Eisenberg, made a number of changes to the first floor of Kilgore Hall. With the assistance of the R&R Construction and Carpentry Projects Shops, the ceilings grid and tile were abated, ceiling tile was replaced, and 4-6 fixtures were removed per room and updated with 2 fixtures. Additionally, the R&R Paint Shop touched up the paint in each room.

 

Work Order Number: 14-60291

Notes:

 

Before Image:

After Image:

Published in .