Marye Anne Fox

Asset:

Marye Anne Fox – Rm 319

Project Manager:

Derek Kristeller

Total Cost:

$2,823

Cost Per Square Foot:

$N/A

Completion Date:

Aug 26, 2014

Narrative:

Installed drain, water line, and dedicated circuit for ice machine. Work was completed in Marye Anne Fox room 319. The project involved core drilling into floor to install drain and water line. Electrical was installed in the wall behind the machine. Work was completed in 5 days.

Work Order Number: 14-67160