Research IV

Asset:

Research IV – Suite 1800

Project Manager:

Tom Moore

Total Cost:

$47,068

Cost Per Square Foot:

$N/A

Completion Date:

Jun 8, 2015

Narrative:

Tom Moore, Project Manager, worked with the Construction, Carpentry Maintenance, General, Sign and Paint Shops to update Suite 1800.  Which included new LED lighting, ceiling tiles and smoke heads.  Also, installed new break room cabinets, carpet, VCT and painted the entire suite.

Work Order: 15-47278

 

Notes:

Before Image:

After Image:

Published in .

Leave a Reply