Centennial Biomedical Campus (CBC) Chilled Water Expansion Project- Advertisement for Bids & Notice of Public Meeting for Proposed Alternate Bids for Preferred Products

Sealed proposals will be received by NC State University. Attention Damian Lallathin, until 2:00 PM on July 13th, 2017 in conference room 101, Administrative Services III Building 2701 Sullivan Drive, Raleigh, NC 27695 and immediately thereafter publicly opened and read for the furnishing of labor, material and equipment for the construction of:

North Carolina State University
Centennial Biomedical Campus (CBC) Chilled Water Expansion Project
SCO# 15-12137-01
NC State# 201420019

Scope includes the replacement of the plant controls system, replacement of an existing 800 ton gas engine driven chiller, condensate and deaerator replacements, electrical upgrades and plant deficiency repair.

Bids will be received for single prime bid contracts.  All Proposals will be lump sum.

The following General Contractors have been pre-qualified to bid this job:

  • Boiler Master, Inc. …………………………………………Greensboro, NC
  • Comfort Systems, USA……………..…………………….Raleigh, NC
  • Freedom Industries, Inc..…………………………………Rocky Mount, NC
  • Jacobs Contracting………………………………………..Winston Salem, NC
  • McDonald York Building Company.……………………..Raleigh, NC
  • Riley Contracting Group, Inc. ……………………………Cary, NC
  • Quate Industrial Service, Inc. ……………………………Durham, NC

Bid documents are available for examination in the plan rooms:

  1. iSQFT; http://www.isqft.com/start/ handles Associated General Contractors plan room.
  2. The local North Carolina offices of Dodge Data and Analytics;
  3. The Eastern Regional Offices of CMD Group in Norcross, GA;
  4. The offices of the Designer: RMF Engineering, Raleigh, NC
  5. The North Carolina Institute of Minority Economic Development, Inc. (NCIMED) Plan and Resource Center at 114 W. Parrish St., 6th Floor, Durham, NC; 919-956-8889 or 919-287-3036
  6. The Hispanic Contractors Association of the Carolinas (HCAC) in Winston-Salem, Charlotte and Raleigh Areas – 877-227-1680;

Continue reading

B104 Lab Renovation, CVM Main Building – Architecture/Engineer Selection

NC State University
Project: B104 Lab Renovation, CVM Main Building
NC State Project #201720027

Description:  Phase I of the project will renovate approximately 7,700 ASF on the First Floor of Module B in the CVM Main Building, built in 1982. This module comprises approximately 3,860 ASF of Pathology teaching lab and support space; 2,320 ASF of office and storage area; and 1,518 ASF of Histology lab and support space. Simultaneous instruction of 100 students occurs in the Pathology lab for the practice of examining and identifying various veterinary pathogens and disease vectors. The intent of the renovation is to retain the existing lab functionality, but expand its footprint to accommodate more flexible and varied teaching pedagogy.

Contact:  For specific project inquiries – Bob Cwikla (919-515-6836) rmcwikla@ncsu.edu

http://facilities.ofa.ncsu.edu/category/ads/

Pre-submittal Meeting:   A Pre-submittal Meeting will be held June 14 at 4:00 pm in Conference Room 301, Administrative Services III, 2701 Sullivan Drive on the NC State campus.  Attendance is encouraged but not mandatory.

Closing Date:  5:00 pm, June 30, 2017

Project Budget:  Total project budget is $2,000,000, which includes all hard and soft costs.  The project is approved through Advance Planning.

Submit Letter of Interest and 330 Form to:
Bob Cwikla
NC State University, Capital Project Management
Box 7520, Raleigh, NC 27695-7520
rmcwikla@ncsu.edu

Download Complete Project Information Here: B104 Lab Renovation CVM Main Building Project Summary

DH Hill Tower and Poe Hall Waterproofing

DH Hill Tower and Poe Hall Waterproofing
NC State Project #201720026

The DH Hill Library Tower North Face, the DH Hill Library Tower South Face, and Poe Hall Exterior are all experiencing waterproofing and leaking issues at expansion joints, control joints, windows, doors, masonry-to-masonry joints, and masonry-to-metal joint. This project will remove all existing caulking and backer rods from these interfaces, clean all surfaces of dirt, paint, and oils, prime all joints, seal all interfaces, re-caulk all interfaces, reseal all joints and seams, and repaint masonry where necessary.

Contact:  For specific project inquiries – Steven R. Bostian (919-515-8059) srbostia@ncsu.edu

http://facilities.ofa.ncsu.edu/category/ads/

Pre-submittal Meeting:  A Pre-submittal Meeting will be held June 6, 2017 at 10:30 AM in Conference Room 301, Administrative Services III, 2701 Sullivan Drive on the NC State campus.  Attendance is encouraged but not mandatory.

Closing Date: 5:00 pm, June 20, 2017

Project Budget:  Total project budget is $725,000

Submit Letter of Interest and 330 Form to:
Steven R. Bostian
NC State University
Capital Project Management
2701 Sullivan Drive Suite 331
Raleigh, NC 27695-7520

Download Complete Project Description Here: DH Hill Tower and Poe Hall Waterproofing Project Summary 2017 05 23

Greek Village Phase 3 Infrastructure- Request for General Contractor Prequalification Submittals

North Carolina State University is seeking qualification statements from general contractors for the Greek Village Phase 3 Infrastructure project located on the South Campus Precinct. This project develops lots 8, 9 and 10 for new fraternity houses. It includes construction of the roads, parking lots, and infrastructure associated with the overall development and implementation of the houses.

To be considered, the contractor must obtain an application package from the NC State University Project Manager and submit a sealed, fully completed qualification document by 5:00 PM, June 22, 2017 to Steven R. Bostian, Project Manager, at Administrative Services Building III, 2701 Sullivan Dr., Suite 331, NCSU, Campus Box 7520, Raleigh, NC 27695-7520.  Application packages will be available electronically on May 30, 2017.  Please contact the project manager via email (preferred) or phone to request a package.  One (1) hard copy of the completed qualification packages must be submitted to the project manager.  Completed qualification packages will not be accepted electronically.

Steven R. Bostian
North Carolina State University
Capital Project Management
919-515-8059
srbostia@ncsu.edu

Download Complete Project Description Here: Greek Village Phase 3 Infrastructure

Notification of Open-End Contracts 2016-2017

On behalf of the Selection Committee, we would like to extend thanks for your firm’s interest, and appreciate the time you spent in preparing your submission.

The NC State Board Of Trustees Buildings and Properties Committee has approved the list of firms to offer professional services on an as-needed basis for NC State University. The complete list can be viewed below.

Download the complete project description here: 2016-2017 OESAD Selections